Abstrakti
A short term scheduling problem from an industrial case is modelled in three different ways. A discretized MILP-model, a heuristic approach and a genetic algorithm are tested. The scheduling task is complicated by a recycle connection. Storage capacity for raw materials and intermediates are restricted. Some productions steps are operated continuously and some in batch mode. A one-week schedule and a two-week schedule are constructed with different models and compared with industrial results. The genetic algorithm outperforms the other approaches, though the computational efforts are larger.
| Alkuperäiskieli | Englanti |
|---|---|
| Otsikko | Computer Aided Chemical Engineering |
| Kustantaja | Elsevier |
| Sivut | 679-684 |
| Sivumäärä | 6 |
| Vuosikerta | 10 |
| Painos | C |
| DOI - pysyväislinkit | |
| Tila | Julkaistu - 2002 |
| OKM-julkaisutyyppi | A3 Kirjan osa tai toinen tutkimuskirja |
Julkaisusarja
| Nimi | Computer Aided Chemical Engineering |
|---|---|
| Numero | C |
| Vuosikerta | 10 |
| ISSN (painettu) | 1570-7946 |
Rahoitus
- The financial support from TEKES, the Finnish Technology Agency, is gratefully acknowledged.